|
Hanson-Wilson Inc. (HWI) provided planning and
design engineering services to Ragnar Benson Inc. for the design-build
of the Global III Intermodal facility for the Union Pacific Railroad
in Rochelle, IL., in an effort to handle the growing rail-truck
freight market in the Chicago area. This is an important addition
to Chicago area freight, which is the world's third largest handler
of international freight after Hong Kong and Singapore. The facility
is on the former Chicago & North Western main line and is located
about 80 miles west of Chicago. Opening ceremonies were held in
August of 2003.
This project represents over a two-year effort by the HWI design
team. The project covers 1,200 acres. The first phase of construction
included four intermodal ramp tracks, a 13 track switching yard
and eight track storage yard, four receiving and departure tracks,
an automated gate processing areas, administrative and maintenance
facilities, an industrial wastewater treatment plant, and a parking
area for 2,200 trailers. The design for a locomotive fueling facility,
service facility, and tank farm are completed and ready for the
next phase of construction.
HWI provided the civil, structural, architectural, electrical, and
mechanical and process designs for the entire facility. Services
included a topographic survey, geotechnical investigation, environmental
investigation, hydraulic study, stormwater management, grading,
paving, site utilities, track design, building design and permitting.
A pipe pile-supported, precast concrete railroad bridge was also
included in the project.
The stormwater management plan required three detention ponds on
site, totaling over 400 acre-feet of detention/retention capacity
to mitigate the site runoff impact on the adjacent Kyte River. Design
services also include locomotive service facilities, the industrial
wastewater treatment facility, underground utility systems and site
utilities. HWI also completed the design for the high-mast lighting
system and underground power distribution throughout the yard. Construction
was done in several phases, with construction beginning in late
2001 and the first phase completed during the second half of 2002.
One of the geotechnical challenges associated with this project
was related to the large volume of fill required over about half
of the site in an aggressive construction schedule. In-situ soils
and fill materials had high moisture contents, which required the
use of lime during placement and compaction of fill materials.
Environmental aspects involved permitting for the Clean Water Act
Section 404;IDNR, Office of Water Resources; NPDES storm water discharge;
industrial wastewater pretreatment and discharge; and fuel storage
tanks. HWI also prepared a stormwater pollution prevention plan
(SWPPP) and conducted cultural resources surveys. Wetlands investigations
resulted in minimal impact and no mitigation was required.
Phase I archaeological investigations were conducted and 10 sites
were identified. The investigation resulted in Phase II surveys
at two of the original sites and a Phase III recovery of artifacts
at one site.
|